Underground services under and beside Queensland's state-controlled roads belong to dozens of owners: power, telecommunications, water, gas, and the Department of Transport and Main Roads (TMR) itself. Locating and working on them brings together three systems that don't always line up: Before You Dig Australia (BYDA) for plans, TMR for approvals and its own assets, and chainage to tie it all to the road. This guide sets out how they fit together.
Before You Dig Australia in brief
BYDA is the national referral service for underground asset plans. It replaced the state Dial Before You Dig services, officially from 1 July 2022.
- It's free. Lodge an enquiry on the BYDA website or app.
- Draw your site. You mark the proposed work area on a map; BYDA notifies the asset owners in that area and they send their plans or a clear notice. Plans usually arrive within minutes, but allow up to two business days, and lodge at least one day before work starts.
- Plans expire. Validity is typically 28 or 30 days from the enquiry. Check the date on each plan, and renew for longer jobs.
- Not everyone is a member. BYDA says most asset owners are members, not all. If an owner doesn't respond, follow up using the contact details on your enquiry confirmation.
- Plans show presence, not position. BYDA is clear that plans detail the presence of underground infrastructure rather than its exact location. Its "5 Ps" are Plan, Prepare, Pothole, Protect, Proceed.
The gap: TMR's own assets
Here's the catch on state-controlled roads: TMR is not a BYDA member. TMR's Non-Transport Utility Management and Design Manual says "not all underground asset owners (including the department) are members of Before You Dig Australia", and makes it the utility's responsibility to contact all plant owners and the local TMR project manager. TMR's earlier utility protocol said its infrastructure must be requested from the relevant TMR district office.
TMR's underground assets in a road corridor can include conduits and pits for traffic signals, road lighting and intelligent transport systems (cameras, message signs, detector loops and their communications), as well as drainage. A clear BYDA response doesn't mean there's nothing of TMR's in the ground, so ask the district office for its asset information as part of your enquiry.
From plans to the ground
TMR treats BYDA information as Quality Level D under the Australian standard for subsurface utility information (AS 5488), the lowest level, and notes that the location on such plans "is typically highly inaccurate". Higher quality levels come from detection on site and, at the top level, from exposing the service by potholing.
- Within road pavement, TMR expects locating to use non-invasive methods such as ground-penetrating radar and electromagnetic induction, and won't generally approve disturbing the pavement just to expose existing services.
- Telstra plant may only be accessed by Telstra-accredited plant locators, and TMR's guidance treats electronically measured depths as a guide that must be confirmed by potholing or vacuum excavation.
- Certified locators: BYDA's enquiry results can show certified locating organisations that service the area; the certification itself now comes from CERTLOC (formerly DBYD Certification), not BYDA.
Your legal duties in Queensland
- Get the information first. Under section 304 of the Work Health and Safety Regulation 2011, the person with management or control of the workplace must take all reasonable steps to obtain current underground essential services information, including location and depth, before excavation starts. They must give it to the excavation contractor, everyone must have regard to it, and it must be kept until the work is finished (or for two years after a notifiable incident).
- Follow the code. The Excavation work Code of Practice 2021 warns that information about existing services may not be accurate and describes potholing, electromagnetic locators and ground-penetrating radar. In Queensland, duty holders must follow an approved code of practice or a method that's at least as safe.
- Electricity has its own code. The Electrical Safety Code of Practice for working near overhead and underground electric lines applies when you're near electric lines, and where both the electrical safety and WHS laws apply, the Electrical Safety Act 2002 takes precedence.
Approvals for work in a state-controlled road
Which TMR approval applies depends on who you are:
| Who | How TMR approves the work |
|---|---|
| Utility owners (public utility plant) | Work must meet TMR's requirements under the Transport Infrastructure Act 1994, sections 77 to 83, including notice before work. Requirements can cover location (including alignment and depth), traffic control, access times, insurance and indemnity. Apply through TMR's online permit portal with TMR's deed of indemnity, following the Non-Transport Utility Management and Design Manual and TMR's standard conditions. |
| Electricity entities | Under the Electricity Act 1994, building or altering lines on a road needs the road authority's written agreement; maintenance and repair don't. |
| Telecommunications carriers | For low-impact facilities, a land access and activity notice to TMR at least 10 business days before work, under the federal Telecommunications Act 1997. |
| Developers and contractors doing utility works | The utility's TMR works reference, then a Road Corridor Permit. |
| Anyone else placing or doing something in the corridor | A Road Corridor Permit under section 50, at least four weeks ahead. |
| Anyone affecting traffic | A Traffic Control Permit as well, applied for by a registered traffic management company, at least 10 business days ahead. |
TMR's utility conditions also expect $20 million public liability cover, RPEQ-certified drawings and as-constructed drawings when the work is done, and suggest registering new installations with a service such as BYDA. For more on the two permits, see Road Corridor Permit vs Traffic Control Permit.
Where chainage fits
Utility drawings and BYDA plans work in coordinates, lot/plan numbers and street addresses. TMR's road network works in road sections and chainages. Tying the two together makes everyone's life easier:
- Applications: TMR asks for the road name and location (nearest feature, town or intersection) on utility applications, latitude and longitude on Road Corridor Permits, and start and end chainages or cross streets on Traffic Control Permit forms.
- Records: the Act requires a utility owner working on plant in a state-controlled road to "prepare records that adequately define the location of the plant on the road". A road section, chainage and offset from the road, with coordinates, does exactly that.
- Traffic management: the traffic guidance scheme and the TMR traffic team will reference your site by chainage.
A useful format for each located service or pothole: "Telstra pit, 10A Ch 25.412, 14 m left of centreline in gazettal direction, lat/long, depth 0.6 m (potholed)".
A practical workflow
- Confirm who manages the road. See state-controlled road or council road?
- Get the chainage range of the works in Chainage and copy the coordinates of the start and end. Use them to draw an accurate BYDA enquiry area, and quote them to the TMR district office when you request its asset information.
- On site, record every mark-out. Drop a pin exactly on each located service, pit or pothole. Chainage keeps the exact position and records the nearest road chainage and the distance from the road. Save it to a layer for each service type (Telstra, Energex, Water, TMR ITS), with notes on depth and detection method and photos of the marks.
- Share and hand over. Give the excavation crew and the client a share link to the project, and export to CSV or GeoJSON for your locating report, as-constructed drawings or the asset owner's GIS. Each row carries the coordinates, road, section, carriageway, chainage and offset.
Chainage records where you marked a service; it doesn't detect or verify services. Always follow BYDA, the asset owners' requirements, the codes of practice and TMR's conditions.
Frequently asked questions
Is TMR a member of Before You Dig Australia?
No. TMR's utility manual says the department isn't a BYDA member, so its underground assets, such as traffic signal, lighting and ITS conduits, won't appear in BYDA responses. Request them from the TMR district office.
How long are BYDA plans valid?
Typically 28 or 30 days from the enquiry; check the date on each plan. For longer jobs, BYDA can automatically renew an enquiry every 28 days for up to six months.
Do BYDA plans show the exact location of services?
No. They show that infrastructure is present, not its exact position or depth. TMR treats them as Quality Level D information. Confirm locations on site with detection and potholing.
Do utility works in a state-controlled road need a Traffic Control Permit?
If the work may interrupt traffic, pedestrians or public transport, yes. A registered traffic management company applies, allowing at least 10 business days.
How should I record the location of a located service?
Record coordinates plus the road section, chainage and offset from the road, the side of the road, the depth and how it was confirmed, with photos. That combination works for TMR, asset owners and GIS.
Sources
- Before You Dig Australia, FAQs, Guide to free plans, Duty of care and Enquiry auto-renew.
- TMR, Non-Transport Utility Management and Design Manual and Utilities.
- TMR, Technical Note TN157.
- Transport Infrastructure Act 1994 (Qld), sections 33, 50 and 77–83; Transport Infrastructure (State-controlled Roads) Regulation 2017, section 11.
- Work Health and Safety Regulation 2011 (Qld), section 304; WorkSafe Queensland, Excavation work Code of Practice 2021 and Electrical Safety Code of Practice: working near overhead and underground electric lines.
- Electricity Act 1994 (Qld), section 102; Telecommunications Industry Ombudsman, Land access guidelines.
- CERTLOC, Become a certified locator.